Variant of Caltagirone – Licodia Eubea

Italy, Sicily
2012-2013
Motorway Viaduct

2750 m
Mixed structure, Road Viaduct
75 m
Span by span

Sicily.

Functional excerpt "Caltagirone variant"

Freeway Licodia Eubea - A19 PA-CT.

In this context, SPIC built three viaducts in 17 months, with a total length of 2,750 m and a total surface area of ​​23,200 m2.

The decks consist of two lateral steel beams and a concrete slab.

SPIC carried out the assembly, transport and launch of the steel structures, for a total weight of 9'450 tons, and built all the reinforced concrete slabs.

For the construction, specific prefabrication and assembly plants were set up by SPIC at each viaduct.

 

Paradiso I viaduct, assembled in 8 and a half months with a caravan.

The viaduct is 725 m long and consists of 11 spans with a maximum span of 75 m and a width of up to 15.55 m, for a total surface area of ​​8,900 m2.

The steel structures had a weight of 2'600 tons.

 

Ippolito I viaduct, assembled in 6 months with a caravan.

The viaduct is 1100 m long and consists of 15 spans with a maximum span of 75 m and a width of up to 12 m, for a total area of ​​13,200 m2.

The steel structures had a weight of 3'800 tons.

 

Ippolito III viaduct, built in seven months with push launch.

The viaduct is 925 m long and consists of 13 spans with a maximum span of 75 m and a width of up to 12 m, for a total area of ​​11,100 m2.

The steel structures had a weight of 3'050 tons.                             

Complex or large works
That we optimize in terms of production and cost